Updated 13 Nov 2026· Reviewed by Nathan Taylor, Head of Operations
A tender process is the formal procedure through which a Contracting Authority invites bids for a construction contract and identifies the most advantageous tender. It typically comprises five stages: procurement strategy and market engagement, preparation of the tender documents, tender issue and clarifications, evaluation and award, and contract award and mobilisation. Under the Procurement Act 2023, each stage is subject to requirements on notices, time limits and transparency.
The appropriate tender process depends on the nature and value of the project and the route to market selected. Where the route to market has not yet been determined, our guide to construction procurement routes sets out the options. This guide explains each stage of the tender process from the Contracting Authority’s perspective, the timescales involved, and how the process differs when calling off from a framework.
What is a tender process?
A tender process is a formal, competitive procedure for awarding a contract. The Contracting Authority defines its requirements and evaluation criteria as part of its procurement strategy, bidders submit priced proposals, and the contract is awarded to the tender that best meets the published award criteria.
The tender process must be fair, transparent and defensible. Contracting Authorities are required to treat suppliers equally, document their decisions and comply with the procurement regulations applicable to the contract.
The 5 stages of the tender process in construction
Stage | What happens | Key output |
1. Procurement strategy and market engagement | Confirm scope, budget, programme and route; test market appetite via issuing an EOI | Procurement strategy |
2. Preparation of the tender documents | Write the specification, pricing documents, award criteria and contract | Tender pack |
3. Tender issue and clarifications | Publish the notice or invite framework contractors to bid; manage clarifications | Compliant tenders received |
4. Evaluation and award | Score bids against the published criteria; notify bidders; observe standstill; publish the notice | Award decision |
5. Contract award and mobilisation | Sign the contract, agree the programme and start on site | Signed contract |
Procurement strategy and market engagement
Before going to market, the Contracting Authority should establish a clear procurement strategy, confirming the scope, the budget and its level of certainty, the programme, and the extent of design completed. These factors determine which call off route is appropriate, and whether early contractor involvement would reduce risk.
Market engagement should inform that strategy. Preliminary market engagement establishes contractor capacity and appetite for the scheme, tests whether the budget is realistic and informs how the works should be packaged. Under the Procurement Act 2023, a Contracting Authority must publish a preliminary market engagement notice before tendering, or explain in the tender notice why it did not.
“The biggest mistake we see is treating market engagement as a tick-box exercise to see who might bid, rather than using it to inform the procurement strategy. Our advice is to use market engagement to firm up the procurement strategy, and to do so as early as possible. When clients do this, we see bidder appetite and project certainty increase.” – Samantha Cousins, Framework Operations Manager, Procure Partnerships Framework
A framework enables this stage to be completed considerably more quickly. Through PPF, an Expression of Interest (EOI) can be run in 3 days, confirming market appetite among pre-qualified contractors before the procurement strategy is finalised. The Framework team can also provide market intelligence on capacity, timescales and pricing within the relevant region.
Preparation of the tender documents
The tender documents set out the Contracting Authority’s requirements and the basis on which tenders will be evaluated. They typically include:
- instructions to tenderers and the timetable
- the specification, drawings and survey information
- pricing documents, such as a bill of quantities, activity schedule or schedule of rates
- the award criteria, their weightings and how each will be scored
- quality questions, including social value
- the form of contract, commonly JCT or NEC (see our guide on the differences between JCT and NEC)
Award criteria should reflect the priorities of the specific project, as criteria that cannot be scored consistently are a common source of challenge. Contracting Authorities using PPF have access to template tender documents and support from the Framework team in setting proportionate, defensible criteria mapped to their specific priorities.
Tender issue and clarifications
Under the open procedure, the Contracting Authority publishes a tender notice on the Central Digital Platform and must allow bidders at least the statutory minimum period to respond. Under a framework, the Contracting Authority instead invites the appointed contractors in the relevant lot and value band to bid through the framework’s call-off procedure(s). As those contractors have already been assessed, the tender period can focus entirely on the project requirements.
During the tender period, bidders will raise clarification questions. Responses should be issued promptly and shared with all bidders, while protecting each bidder’s commercially sensitive information. Site visits and mid-tender meetings help bidders to price accurately and reduce the assumptions and qualifications in their submissions, which makes tenders easier to compare.
Evaluation and award
Each tender should be evaluated strictly against the published criteria and scoring methodology, with the reasons for every score recorded. This record forms the audit trail for the award decision.
Under the Procurement Act 2023, a public contract must be awarded to the most advantageous tender. For a competitive tendering procedure, the Contracting Authority must then provide each bidder with an assessment summary, publish a contract award notice and observe a standstill period of eight working days before entering into the contract. Call-offs under a framework are subject to different requirements, which are set out in the framework’s call-off procedure.
When Contracting Authorities procure through a framework, they retain control of the decision, evaluating the tenders and awarding the contract. Procure Partnerships Framework provides access to pre-qualified contractors, template documents and procurement support throughout, and contractor pricing is independently reviewed against fixed Framework rates.
Contract award and mobilisation
Once the standstill period has ended, the contract can be finalised and signed, and the programme, key personnel and reporting arrangements agreed. On a two-stage tender, the first stage is often a pre-construction services agreement (PCSA), with the main contract following once the price is agreed. Our guide to the post-tender process covers this stage in more detail.
Performance measures, including key performance indicators and social value commitments, should be agreed before work starts. On Procure Partnerships Framework, a minimum 12% social value add is mandated on every project, KPIs are benchmarked against an 80% threshold, and suppliers are monitored to pay invoices within 30 days.
How long does a tender process take?
The duration depends on the route chosen and how complete the tender documents are. The Procurement Act 2023 sets minimum periods for bidders to respond; document preparation, evaluation and the standstill period are additional.
Route | Minimum time for bidders to respond | Other factors affecting the timetable |
Framework call-off | Set by the framework’s call-off procedure | No selection stage, as contractors are already assessed; through PPF, EOIs can be run in 3 days and construction projects typically reach the market in 4–6 weeks |
Open procedure | 25 days if tenders are electronic and all documents are issued with the notice; up to 35 days otherwise | Selection, then evaluation of every bid received; 8 working days’ standstill |
Competitive flexible procedure | At least 25 days to request to participate, followed by a tendering period | Each additional round of shortlisting or negotiation |
Source: Cabinet Office guidance on time periods. A qualifying planned procurement notice can reduce the tendering period to 10 days.
Through Procure Partnerships Framework, construction projects typically reach the market in 4–6 weeks and professional services in 2–4 weeks, which is 2–3 months faster than an open tender. Removing the pre-qualification stage reduces procurement timescales by approximately 8–12 weeks. Client feedback across 24 recent local authority projects shows approximately 120 days of procurement officer time saved per project, compared with a standalone procurement exercise.
Which type of tender process should you use?
Tender type | How it works | Best suited to |
Framework call-off | A mini competition between the framework’s pre-qualified contractors, or a direct award where the framework’s rules permit | Most public sector construction schemes, particularly where programme certainty, compliance and access to vetted regional contractors are priorities |
Single-stage | Contractors price a complete design in one stage | Schemes where the design is complete, typically at RIBA Stage 4 |
Two-stage | A contractor is appointed early on fees and preliminaries, and the price is agreed as the design develops | Complex schemes, tight programmes, or where contractor input will improve buildability and cost certainty |
Open procedure | Any supplier may bid in a single stage | Simple or highly specialist requirements, where the Contracting Authority has the resource to assess a large number of bids |
Competitive flexible procedure | A procedure designed by the Contracting Authority, which may include shortlisting and negotiation | Complex requirements that justify a bespoke procedure. Under Section 21 of the Procurement Act 2023, you must design the procedure before publishing the tender notice and clearly explain all planned stages, limiting flexibility to add or change stages after the tender notice is published. |
Single-stage and two-stage tendering are not alternatives to a framework. Both can be run as a call-off through Procure Partnerships Framework, allowing Contracting Authorities to retain the tendering approach best suited to the project while benefiting from pre-qualified contractors and Framework support.
What is a closed tender process?
A closed tender (also referred to as a restricted or selective tender) invites only a shortlist of suppliers to bid, whereas the open procedure allows any supplier to submit a tender. A mini competition under a framework operates in a similar way to a closed tender: only contractors already appointed to the framework, and assessed for capability and financial standing, may take part.
When is Procure Partnerships Framework the right route?
The framework is designed for public sector bodies that need a compliant, efficient route to market for construction, infrastructure, professional services, decarbonisation and retrofit, or demolition projects. It is used by over 150 public sector organisations and offers:
- pre-qualified contractors and consultants across nine regions of England, organised by value band
- EOIs in 3 days, and typically 4–6 weeks to market for construction projects
- template documents and support from the Framework team, from early market engagement through to final account
- contractor and consultant pricing independently reviewed against fixed Framework rates, with open-book pre-construction and at least 3 quotes per package
- a minimum 12% social value add on every project, with KPIs benchmarked against an 80% threshold
There is no fee for Authorities to access the Framework. A levy, paid by the appointed contractor, is set as a percentage of construction value.
It is important to note a framework will not suit every project. Very minor construction works and highly specialist requirements may be better served by another route, and the Framework team will advise on this at the outset.
Which procurement rules apply?
The Procurement Act 2023 came into force on 24 February 2025. It applies to procurements started on or after that date. Procurements and frameworks started under the Public Contracts Regulations 2015 continue under those rules until they end.
From 1 January 2026, the threshold for works contracts is £5,193,000 (PPN 023). Below the threshold, fewer of the Act’s procedural rules apply, but some transparency duties still do. Contracting Authorities should confirm which regime applies before commencing a procurement. Further detail is available in our Procurement Act 2023 guide.
FAQs
What are the stages of the tendering process?
The main stages are procurement strategy and market engagement, preparation of the tender documents, tender issue and clarifications, evaluation and award, and contract award and mobilisation.
How long does a tender process take?
Under the Procurement Act 2023, bidders must be given at least 25–35 days to respond in an open procedure, with preparation, evaluation and an eight working day standstill period in addition. A framework call-off is usually considerably quicker: through PPF, construction projects typically reach the market in 4–6 weeks.
What is the tender evaluation process?
The Contracting Authority scores each tender against the award criteria and weightings published in the tender documents, records the reasons for each score, and identifies the most advantageous tender.
Who evaluates tenders on a framework?
The Contracting Authority. On PPF, the Contracting Authority evaluates the tenders and awards the contract, with procurement support available from the Framework team throughout.
What is the difference between single-stage and two-stage tendering?
Single-stage tendering requires contractors to price a complete design in a single stage. Two-stage tendering appoints a contractor earlier and agrees the price as the design develops.
Planning a construction tender? Get free advice from our experts on the most appropriate route to market and timescale for your project. Or explore our frameworks below.
Discover our Frameworks
Looking for expertise on the Stages of the Tendering Process in Construction Procurement? Search for specialist frameworks in your region.