Construction has commenced on the £18.5m redevelopment of Block A at Lambeth College’s Clapham Campus, creating modern teaching, learning and administrative space for South Bank Colleges. 

This project is being delivered by Contractor Partner Neilcott Construction, and procured via the Procure Partnerships London Construction Framework, using a two-stage design and build route.

Making better use of the campus

The scheme combines the refurbishment of Block A with the demolition of the existing sports hall in the north wing of the Henry Thornton Building. In its place will come a new four-storey extension, adding educational floorspace, cycle parking and associated external works.

Together, the works make better use of the existing campus and provides flexible spaces for teaching, learning and administration, along with new facilities including a dining hall and shop.

For an education project of this scale, South Bank Colleges needed a route to market that could bring a capable contractor on board early to mobilise quickly. The Procure Partnerships Framework gives education clients access to pre-qualified, continuously vetted Contractor Partners, with a choice of call-off routes to suit the project requirements.


Shaping the project before it reached site

South Bank Colleges used a two-stage design and build route through the Procure Partnerships Framework, appointing Neilcott early to support the client and design team through pre-construction. This gave the college a way to bring contractor expertise into the project well before the main works began.

During stage one, Neilcott reviewed buildability, logistics, programme, sequencing, risk and cost. That early input was particularly valuable on a live campus, where the sports hall demolition, temporary works and the need to manage disruption all had to be planned from the start.

This approach supported faster mobilisation, greater cost certainty and reduced delivery risk. It also gave the team time to develop the design, agree methodology and prepare the site strategy ahead of the main works.

Learn more about how our framework options can support early contractor involvement today: https://procurepartnerships.co.uk/how-it-works/ 

 

Preparing for work on a live campus

Before intrusive works began, the team planned the hoarding line, site accommodation, tree protection zones and environmental control measures. Initial works include isolating and stripping out existing services in Block A, followed by temporary propping to make the building safe ahead of the sports hall demolition. Noise management has been identified as a key consideration for the surrounding campus and community.

Because the early planning took place during pre-construction, the college began the main works with the site strategy already agreed. Throughout delivery, Neilcott reports monthly through our project management platform against KPIs for cost, time, health and safety, sustainability, and client satisfaction, giving South Bank Colleges and our in house operations team a clear view of progress.

 

Creating opportunities for local people

Social value will focus on education, employment and skills linked to the college environment. The project team plans to offer student engagement, work experience, careers activities, supply chain involvement and site-based learning where it is safe and practical.

It will also look for opportunities to support local spend, responsible waste management and engagement with the wider Lambeth community, as part of the framework’s minimum 12% social value requirement.

Procure Partnerships Frameworks dedicated Social Value advisor will supports the project throughout delivery, helping to monitor commitments, verify evidence and track progress. This gives the college visibility of the social value being delivered and helps ensure commitments made at tender stage are followed through on site.

 

Chris Witterick, Framework Manager (South), Procure Partnerships Framework, said:

“It has been a pleasure working with Neilcott Construction on this project, which has not been without its challenges. In light of a funding deadline, we were able to support the client both at pace and in a compliant way to get to their desired outcome. I’m looking forward to following the progress of this scheme and the many possibilities it will open up to young people in London.”

 

Andrew O’Connor, Project Coordinator, Procure Partnerships Framework:  

“It was a pleasure to help bring the Lambeth College project to life, from the initial tender stages through to the successful award The process presented a number of challenges along the way, requiring clear communication and a proactive approach to managing the various requirements and differing priorities of those involved. We are delighted to have achieved a positive outcome for the client and look forward to seeing the project progresses in the future.”

By combining early contractor involvement with a compliant, pre-qualified route to market, the Procure Partnerships Framework has helped South Bank Colleges set up this redevelopment for efficient delivery.

 From £50k to £30m+, discover a faster, more collaborative route to successful project delivery with the Procure Partnerships Framework, explore your framework options https://procurepartnerships.co.uk/frameworks/