Construction has commenced on the new Electrical Sub-Station A4 at the University of Leeds, a key part of the University’s Aged Infrastructure Renewal Programme.

Delivered by Contractor Partner VINCI Building, the £10m+ project started on site on 28th September 2026. It is split into two phases, with Phase 1 planned to complete in July 2027 and Phase 2 running from August to October 2027.

The project was procured via the Procure Partnerships Yorkshire Framework, using an NEC4 Option A contract.

Renewing the University’s electrical backbone 

The scheme will replace and modernise key electrical infrastructure serving the campus. Phase 1 delivers a new brick and block Electrical Sub-Station A4, below-ground service trenches and precast troughs, and internal electrical upgrades in existing buildings, including new low-voltage panels in the EC Stoner building. Once the new substation is energised and the switchovers are complete, Phase 2 will decommission and demolish the existing substation and deliver hard and soft landscaping.

The project will maintain the reliability and resilience of the University’s electrical network, reduce the risk of service disruption and support the future needs of the estate.

Education is one of the sectors the Procure Partnerships Framework serices, giving universities access to pre-qualified, continuously vetted Contractor Partners for complex estate projects such as this.

Extending a partnership through the framework

The University needed a compliant route to appoint VINCI Building, because the Aged Infrastructure works extend its existing Net Zero Carbon Delivery Partner appointment. The framework made that possible, allowing the University to bring the scheme into its existing delivery team and carry across lessons learned from the Worsley Building Pre-Construction Services Agreement (PCSA).

For the University, that meant continuity and a smooth path to appointment. For VINCI Building, it extended its pipeline of work with the client. We advise clients on the right call-off route and contract option for each project.

Delivering safely on a live campus 

The works will be delivered within a live university environment. They include concrete foundations, an off-site packaged substation clad in situ, and prefabricated ducts connecting to the existing network. These ducts are installed using vacuum excavation (Vac-Ex) techniques to significantly reduce the risk of disrupting existing underground services. An Arboricultural Report has informed the approach to working around protected trees, and the University will carry out independent vibration monitoring of adjacent buildings.

Throughout delivery, VINCI will report monthly through our secure platform against KPIs covering cost, time, health and safety, sustainability, fair payment and client satisfaction. This gives the University and our team ongoing visibility, so potential emerging risks can be addressed and avoided.

Social value with clear targets

Social value is a contractual requirement on every Procure Partnerships Framework project, with a minimum of 12% social value add. For this project, VINCI Building has set specific targets, including:

  • 140 apprentice weeks
  • 5 employment opportunities
  • 10 training weeks
  • 4 education activities and 2 community engagement activities
  • 50% local labour, 30% local spend and 50% SME spend
  • A 95% payment practices target
 

The programme builds on established local relationships. The Construction Explorers Programme at Thorner Primary School will continue with four further sessions, and student placements and careers sessions will give University of Leeds students first-hand experience of live construction. The project will also support Ahead Partnership, which works with young people at risk of disengaging from education or employment, and Smart Works, as well as local foodbanks and community groups.

Our in-house Our in-house Social Value and Sustainability Lead verifies the evidence behind each outcome, with reporting tracked monthly. Learn more about how we can support your social value initiatives here 

 
Adrian Leigh, Contracts Manager at VINCI Building, said:

“We are delighted to have worked closely with the University and its design team to navigate the challenges of developing a clear brief that meets its complex requirements. We are now excited to be progressing a scheme that will make a positive contribution to the estate, supporting future ambitions while enhancing the student experience and environment.”

Paul Thomas, Interim Development Project Manager, University of Leeds, said:

“VINCI Building has demonstrated a collaborative and professional approach throughout the development of the A4 project. Their early engagement and commitment to understanding the University’s requirements have been instrumental in progressing a solution that aligns with our strategic objectives and the needs of our students. We look forward to the successful completion of the facility and the positive contribution it will make to the University estate.”

Jaime Stanton, Framework Manager (North), Procure Partnerships Framework, said:

“The A4 substation project is an important investment in the University of Leeds’ infrastructure, helping to modernise ageing electrical systems and improve the resilience of the estate for the future. Through the framework, Procure Partnershpis supports a compliant and efficient procurement route, helping the University and its delivery partners work together to manage the phased works safely while minimising disruption to the live campus.”

Samantha Cousins, Framework Operations Manager, Procure Partnerships Framework, said:

“It was great to work alongside the team at Uni of Leeds to support the appointment of VINCI Building through the Procure Partnerships Framework. The framework provided a compliant procurement route, enabling continuity with the University of Leads’ existing delivery team and supporting a collaborative approach to progressing the scheme. It’s rewarding to see the project move forward, helping to modernise essential infrastructure across the university estate.”

Whatever the scale of your next project, discover how the Procure Partnerships Framework, covering £50k to £30m+, can help you deliver faster and more collaboratively throughout the entire project life cycle: https://procurepartnerships.co.uk/